The following describes the logistics plans for Fall construction projects that will impact campus pedestrian and vehicular pathways.


Messick to McGinnis HVAC Piping

Contractor: TBD
Engineer: Dewberry
Mobilizing (Estimate): TBD
Project Completion: TBD (4 weeks)
Project Manager: Elizabeth Weber

Map of Messick and McGinnis construction area. Described below.

Logistics Details: The construction laydown area is located between Messick Building and McGinnis and will be surrounded with fencing. Pedestrian Walkways between Student Plaza and Messick Building will remain open during construction.


Building 141 PASS Clinic Renovation

Contractor: TBD  
Designer:
MHA Works
Mobilizing (estimated): TBD
Project Completion: TBD
Project Manager: Sophiat Alaran – FEAS

Map of Building 141 construction area. Described below.

Logistics Details: The parking lot behind building 141 will be used for Construction parking and laydown for this project and for the concurrent roof project. Traffic for Reade, 1st and Cotanche Streets will not be affected.


Clark-LeClair Renovation & Expansion

Contractor: Hamel Builders
Design Team:
CRA 
Mobilizing (estimated): September 2025
Project Completion: December 2026
ECU Project Manager: LL Everett

Map of Clark-LeClair construction area. Described below.

Logistics Details: The parking area between Clark-LeClair and Charles Blvd. will be fenced off for contractor parking and laydown, as will a portion of the parking lot immediately in front of the Stadium. Vehicular traffic on roads around the stadium will not be impacted.


Indoor Practice Facility

Contractor: Hamel Brothers
Designer: CRA
Mobilizing: May 2025
Project Completion: November 2026
Project Manager: LL Everett

Map of Indoor Practice Facility construction area. Described below.

Logistics Details: The Indoor Practice Facility Building Site will be fenced off. This fencing will take up a portion of the parking off of Charles Blvd. and the tennis court area. Normal traffic flow will continue outside of the fenced areas.


Whichard Building Comprehensive Renovation

Contractor: Muter Construction, Inc.
Designer: HH Architecture
Mobilizing (estimated): April 1, 2025
Project Completion: April 16, 2026
Project Manager: LL Everett

Map of Whichard Building construction area. Described below.

Logistics Details: Contractor parking along Beckwith Drive and E. 5th Street will be marked. Vehicular traffic should not enter Wright Circle. Pedestrian traffic will need to follow the designated pathways in and around the Trustees Fountain and adjacent buildings.


Greene Residence Hall Fire Alarm Panel Relocation

Contractor: DesignCo
Designer: NV5 Engineers & Consultants, Inc.
Mobilizing (estimated): July 28, 2025
Project Completion: TBD
Project Manager: Sophiat Alaran – FEAS

Map of Greene Residence Hall construction area. Described below.

Logistics Details: Contractors will have permits to park in specific spaces at the Life Sciences and Biotechnology Building. There will be two parking spaces for contractors to use for loading and unloading supplies between Greene Residence Hall and Eakin Student Recreation Center. Those spots will be blocked off when not actively loading or unloading.


Howell Science South Building

Contractor: Muter Construction, Inc.
Designer: BSA LifeStructures, Inc.
Mobilizing (estimated): May 2024
Project Completion: Feb 2026
Project Manager: LL Everett – FEAS

Map of Howell Science construction area. Described below.

Logistics Details: Construction laydown areas located south of the Howell complex will be fenced off. The Bus Stop on Ormond Way will be pushed back 2 spaces. Pedestrian pathways will be indicated with directional signage (includes ADA access.)


Modernize Four Elevators – Messick and McGinnis

Design Build Team: T. A. Loving / Progressive
Contractor on Site:
May 12, 2025
Project Completion: July 29, 2025 (McGinnis); August 20, 2025 (Messick)
Project Manager: Michael Talton

Map of the Messick and McGinnis construction area. Described below.

Logistics Details: Contractor parking and laydown areas will be fenced off on Alumni Lane, and between Messick Building and The School of Theatre and Dance. The pathway between Messick Building and The School of Theatre and Dance can be accessed by pedestrians via a ramp and stairs. Vehicular traffic along Alumni Lane and Leary Court will not be impacted. Elevators will not be operating during this construction period.


Nursing Classroom Upgrades

Contractor: Berry Building Group
Designer: Davis Kane
Mobilizing (estimated): July 2025
Project Completion: March 2025
Project Manager: Jordan Delia

Map of nursing classroom construction area. Described below.

Logistics Details: The Contractor for this project will have two marked parking spaces available to them near the building. That and the material staging area, located at the end of the service access between the College of Nursing Building and Ross Hall, should not affect main traffic flow – vehicular or otherwise – around the College of Nursing.


Warren Life Sciences Advanced Energy Recovery AHU-1

Contractor: MechWorks
Designer: DSA Engineering
Mobilization: TBD
Construction Complete: TBD
Project Manager: Dan Baker

Map of Warren Life Sciences Building construction area. Described below.

Logistics Details:

  • Area of work within the Warren Life Science Building shall be limited to mechanical room 155. Any other access shall be specifically requested and coordinated with ECU construction project manager.
  • Access to the mechanical room shall be provided through the exterior roll-up door.
  • The contractor is allowed to use the grass area ajacent to the building generator for material laydown. The contractor is responsible for providing fencing and security if materials are stored outdoors.
  • Large material deliveries shall be coordinated with the ECU construction project manager if West Campus Loop Lanes need to be blocked. Access to the loading dock area shall be maintained during at all times.
  • Anticipated delivery pathway from Stantonsburg Rd is down service drive and the West Campus Loop to Moye Blvd.
  • The contractor will need to be aware of the nearby Brody building renovation and ongoing site improvements in the area.
  • The contractor is responsible for providing temporary restroom facilities for workers. Access to building restrooms will not be provided.
  • Parking shall be coordinated with ECU construction project manager. Grass parking within the laydown yard and campus visitor parking is available.

MC Replacement Steam to Whichard Building Phase 2

Contractor: Cost Effective Maintenance
Designer: Dewberry
Mobilizing (estimated): March 2025
Project Completion: October 2025
Project Manager: Jordan Delia – FEAS

Map of the Whichard Building Steam construction area. Described below.

Logistics Details: The construction work and laydown area will be located at the intersection of Wright Circle and Beckwith Drive. Vehicular traffic should not enter Wright Circle. Pedestrian traffic will need to follow the designated pathways in and around the Trustees Fountain and adjacent buildings.